Friday  4-9-04

Today I went to Franklin at 7:00am and they were closed, not open till 8:00am.  Went back to get the truck and went and unloaded the tools. 

A few minutes later, BMC showed up with the correct I-Joists (7:30).  We unloaded them and loaded up the wrong ones.

Dad and I started putting up the stem walls after drilling the holes.  We also oiled the forms with a weed sprayer.

We went into town and fixed a window at an apartment, then went to Franklin and bought some more concrete nails and concrete cleates since I need 30 more.

When we got back, Dan were there to do his inspection which I scheduled for next Monday...  His secretary put it in his schedule on the wrong date.

We then started putting up the walls. 

Matt got there at 3:30ish, and then Ron and his son showed up about 5ish to help.

We worked until 9:30 and finished all the perimeter walls (rebar installed and whalers installed, vents installed).

Tomorrow we will make the interior forms, finish some rebar work. 

****We need a bigger window for the living room, the back bedroom needs to be adjusted to 15 feet wide inside..

P4090685.JPG
P4090685.JPG
(858KB)
P4090686.JPG
P4090686.JPG
(840KB)
P4090687.JPG
P4090687.JPG
(869KB)

P4090688.JPG
P4090688.JPG
(860KB)

P4090689.JPG
P4090689.JPG
(824KB)